Sanofi Pasteur

 
Project Name: Sanofi Pasteur
Cloke-Kirby Construction undertook this project in October of 2006. The existing Pertussis (whooping-cough) facility was in need of expansion and total systems upgrade.  The facility is one of only 2 facilities in the world to supply this specific vaccine, the other of which was shutting down on a specific date thus making the completion date of September 2007 non-negotiable.  To complete this project the entire facility was required to be shut down.  The process of building qualification and systems validation required a 3 month window in order to commence production.

Scheduling required evening shifts, 7 day work weeks, continuous coordination and seamless schedule phasing.  The project was successful as Cloke-Kirby completed work on time and within the specified budget.
Location:    North Toronto, Ontario
Tenant: Pharmaceutical
Area:
12,000 sq. ft.
Contract Type: Stipulated Sum
Schedule: 10 months
Project Highlights: Only facility in the world to produce
a specific vaccine.
Architect / Designer: David Peters Architect
Mechanical Consultant: SNC - LKM
Electrical Consultant: SNC - LKM
Challenges: Conforming to Schedule